US power grid operator and GO15 member PJM has announced the completion of Phase I (System Impact Studies) for 306 proposed generation projects as part of the operator’s new interconnection process. These requests are expected to clear PJM’s study process and be ready for construction by mid-2025.
More than 200,000 MW of projects should be studied over the next two years to help American states advance their energy policy goals, according to Aftab Khan, Executive Vice President Operations, Planning and Security at PJM.